Tall Oak Midstream II LLC is holding a nonbinding open season through April 20 for its TOM Midcon Transport residue gas pipeline project, which would serve Midcontinent producers with increased takeaway capacity.

On offer is firm service from Tall Oak’s Carmen Plant in Alfalfa County, OK, for deliveries at the Canadian-Blackwell central delivery point on Southern Star Central Gas Pipeline Inc. The Carmen Plant is connected to Panhandle Eastern Pipe Line Co. and ONEOK Gas Transportation LLC for residue gas deliveries.

Tall Oak customers have requested additional residue gas takeaway capacity and market flexibility through a proposed interconnect with Southern Star Central, the company said.

The project would consist of about eight miles of 12- or 16-inch diameter pipeline to the point of interconnect. Plans are to be refined based on shipper interest following the open season.

“Shippers that submit shipper nomination forms through this open season are expected to execute binding precedent agreements following the completion of the refined project design, which is expected before April 30, 2017,” the company said.

For information, check the open season notice, or contact Blake Burger, director of commercial development, (405) 888-5585, bburger@talloakmidstream.com; or Miranda Davis, manager of gas scheduling and contract administration, (405) 888-5585, mdavis@talloakmidstream.com.